17 Week New Home Construction Schedule
The following 17 week new home construction schedule represents the average time it takes to build a standard detached single family home. Please realize that home building schedules are not set in stone. Weather, material shortage, or labor shortage could impact the time frame outlined. In addition your builder’s procedures and schedules may vary due to regional differences.
17 Week New Home Constructions Schedule
Week 1
Stake out lot
Excavate foundation
Form footings
Pour footings
Strip footing forms
Footing inspection
Week 2
Form foundation walls
Pour foundation walls
Strip foundation forms
Damproof/waterproof foundation
Foundation wall inspection
Install water and sewer laterals
Water service inspection
Underdrains system installed
Sewer inspection
Week 3
Backfill foundation
Rough-in underground plumbing
Rough-in underground plumbing inspection
Week 4
Prep basement floor
Prep garage floors
Install gas laterals
Install electric laterals
Pour basement concrete floor
Pour garage concrete floor
Deliver lumber, trusses, I-beams etc.
Week 5
Start framing
Week 6
Framing continued
Framing inspection
Week 7
Rough-in HVAC
Rough-in HVAC inspection
Rough-in plumbing
Rough-in plumbing inspection
Gas line air test inspection
Week 8
Electrical rough-in
Electrical rough-in inspection
Start siding
Start roofing
Week 9
Order cabinets
Start masonry
Install fireplace
Fireplace inspection
Plumbing tip-out and water test
Install soffit and fascia
Week 10
Install batt insulation
Install electrical meter
Install gas meter
Install water meter
Insulation Inspection
Week 11
Install and tape drywall/wallboard
Install eavstrough/gutters
Week 12
Paint exterior
Exterior concrete work
Deliver and Install cabinets
Start interior trim
Week 13
Paint interior
Install flooring
Week 14
Install countertops and backsplash
Deliver and install lights
Install electric trim
Install plumbing trim
Install HVAC trim
Week 15
Install shower doors and mirrors
Check drywall/wallboard
Clean, sweep and install carpet
Week 16
Install cabinet hardware
Final clean and test fireplace, HVAC
Test air tightness, combustion safety
Paint touch-up
Start construction deficiency list
Final building inspection
Week 17
Interior cleaning
Buyer’s walkthrough
Deficiency and defect corrections
Closing
|